Wednesday, 17 July 2013

17th July 2013: Pool In!

Pool is in the ground! Now we just need to do some landscaping... OK, a lot of landscaping! 

Saturday, 13 July 2013

13th July 2013: Cladding Continues...

A few more panels of shadowclad ply to go on and plaster finishing work to do. Unfortunately the plasterer is away now for a few weeks!


13th July: Front Door Arrives


Front door in now so the house is all closed up.

Cladding just about finished so the boys and start on the interior soon!

Sunday, 7 July 2013

6th July - Interior Progress



Looking into the kitchen / family / dining area...

Imagination required.











Our bedroom and bathroom!

6th July - Cladding Going On





Concrete panels going on the living areas for plastering.




Shadowclad plywood on the boys bedrooms.

6th July 2013: Doors and Windows In

Nearly all the doors and windows are in now - just the front entry door left to go.

Cladding prep work underway.